👀🤔Kalashnyk’s friend, deputy Lesya Zaburanna, who heads the temporary investigative commission on building defenses in the Kyiv region, says that contractors, after receiving over 800 million UAH in advances, performed work worth only 2,79% of that amount.
In this way she allegedly refutes the claim of Kalashnyk’s former deputy, who asserted that contractors had not received sufficient funds for the work. Zaburanna says that some small contractors performed work even without advances, while large contractors completed a much smaller percentage of work relative to the funds they had already received.
Contractors have already been paid 823,99 million UAH in advance... At the same time, by preliminary acceptance certificates for completed construction works, only 23,02 million UAH of advances have effectively been settled - 2,79% of the paid advance. An additional 87,45 million UAH was paid separately under certificates of completed works.
Thus, about 801 million UAH in advances remain unaccounted for by acceptance certificates. This is not equivalent to established damages, but it requires an immediate verification of the actual use of funds, the volume of work performed, and the materials delivered.
Almost the entire contracting portfolio, formed without holding open tenders in Prozorro, is concentrated in three companies.
LLC “Consulting-Bud” - 14 contracts for a total of 926,85 million UAH. The company received 439,85 million UAH in advances, of which 15,48 million UAH have been settled by certificates.
LLC “UBK ‘Y.B.I.S.I.’” - 9 contracts worth 644,68 million UAH. It received 324,80 million UAH in advances, of which 7,53 million UAH have been settled by certificates...
LLC “BK Kyiv Facade” - 2 contracts for a total of 122 million UAH. The company received 59,34 million UAH in advances, of which, according to the provided summary, none of the hryvnias have been settled by certificates.
Special attention deserves LLC “IZI GROUP.” Under contract No. 74-26 dated 14 July 2026 of the year, with a value of 52,70 million UAH, the company, without receiving any advance payments, provided the declared construction readiness of the facility at the level of 56%.