Automatically translated version. May contain inaccuracies compared to the original.
“Kyivzelenbud” 11 September commissioned LLC “SK Stroyinvest” to repair a park for 88,56 million UAH.
This is reported in “Prozorro.”
By the end of 2027 year they must renovate the park near the House of Culture of DVRZ in the Dnipro district. The contract includes drilling a well to a depth of 26 m, installing a water supply, a pumping station and an irrigation system, a dry fountain, sports and playgrounds for younger and middle-age children, including an inclusive playground, as well as an exercise area for adults and a dog-walking area. They must also arrange park and running paths, a pergola platform, a utility building, external video surveillance, install benches and trash bins, and landscape the area.
The work is financed from the local budget. This year 14,40 million UAH is allocated, and in 2027 year – 74,16 million UAH.
The project was commissioned from LLC “Ukrainian Main Design, Survey and Research Institute for Reclamation and Water Management Construction.” The positive expert report was issued by LLC “UK Ekspertyza.” The contract price is fixed and includes 644 thousand UAH for inflation and 473 thousand UAH to cover risks (amounts and prices hereafter are shown with VAT).
In the estimate, prices for material resources are close to or below market levels. For example, concrete B20 (M350) was ordered at 4 210 UAH/cu. m. Kovalska Group sells concrete B20 P1 F200 W6 at 5 064 UAH/cu. m.
Polyethylene PE 100 SDR-17 pipes with diameter 110x6,6 mm were accounted for at 439 UAH/m. “Trubpolimergroup” offers them at 389 UAH/m, “Epicenter” at 470 UAH/m, and “Armashop” at 528 UAH/m.
Technoelast EPP roofing felt of unknown thickness was ordered at 352 UAH/sq. m. The Kub base sells Euro-roofing felt Sweetondale Technoelast EPP 5,2 at 397 UAH/sq. m. “Khata Kryta” offers Technoelast EPP 4.0 at 232 UAH/sq. m, and “BudMart” at 186 UAH/sq. m.
At the same time, the largest items are listed without technical specifications, which makes it difficult to compare them with market prices. For example, 10,72 million UAH is allocated for the dry fountain, 4,80 million UAH for the play complex, 988 thousand UAH for a rope play complex, and 915 thousand UAH for a trampoline.
A potential participant, in particular, asked the contracting authority about item ¹357 of the final resource statement. It describes in considerable detail a two-layer surfacing system: the lower layer – SBR rubber crumb fraction 1-4 mm on polyurethane adhesive with thickness 10 mm, the upper – EPDM rubber crumb fraction 1,5-3 mm on polyurethane adhesive with thickness 6 mm. The total thickness of the surfacing should be 16 mm, color execution is specified.
However, the documentation does not specify the type of polyurethane binder (aromatic or aliphatic), the proportion of EPDM in the upper layer, colors by the RAL scale and their layout scheme, performance indicators according to DSTU EN 14877 for sports zones, nor requirements for the concrete and asphalt concrete base – its flatness, residual moisture, pull-off strength, priming and deformation joint parameters.
In addition, the bill of quantities foresees laying both layers of the surfacing exclusively by hand over the entire area – 1 607 sq. m. A mechanized method of installation is not provided for in the estimate.
In response, the contracting authority stated that all technical, quality and functional characteristics of the surfacing are defined by the approved design and estimate documentation, which passed an expert review. Therefore, in its opinion, there is no need to additionally clarify these parameters within the procurement procedure.
The average monthly wage for one worker under full employment and job grade 3,8 is 42 888 UAH. The average salary for vacancies in the construction industry on the Work.ua portal in Kyiv is slightly higher – 47 500 UAH.
The firm received the contract without competition because no one else showed up for the open tender.
To participate in the tender, one had to provide an equivalent contract for construction, reconstruction, or major repairs specifically of an improvement project. In addition, participants had to agree to possible payment deferral for the period of martial law in Ukraine, and also for six months after its termination or cancellation, depending on actual financing.
Acting general director of “Kyivzelenbud” is Olga Manko, and the authorized procurement officer is Yaroslava Kanivchenko. The municipal enterprise is managed by the Department of Ecology of the KMDA, headed by Pavlo Ivanov.
The owner of “SK Stroyinvest” through JSC “Closed Non-Diversified Venture Corporate Investment Fund ‘Terranord Capital’ ” is Denys Ostrovskyi.
The scandalously notorious firm has received government contracts worth 11,9 billion UAH in the Dnipropetrovsk region since 2016, when the Holyk-Reznichenko group and the Dubynskyi brothers were in charge there. That group also had working relations with the Filatov-Korban group that governs in Dnipro.
Two years ago, Bihus.Info published correspondence between Yurii Holyk and the then-owner of “SK Stroyinvest,” Denys Ostrovskyi. In it they discussed obtaining budget funds for hospital repairs under the “Great Construction” program.
Hanna Kyslyakova, “Nashi Hroshi”
Document: PDF proof of the original version of the news item "Юрій Голик, якого називають казнокрадом, отримає від Кличка майже 90 мільйонів гривень: «Київзеленбуд» без проведення конкурсу передав підряд його ком...". It records the publication content at the moment of the first scan, the preservation date and the source: Rozsliduvach.