The executive committee of Kalynivka village council plans to purchase four diesel generators with a total expected cost of 2,30 million hryvnias. The equipment will be procured to provide backup power, including within programs in the education sector and emergency response and recovery.
This was learned by Kyiv Vlada from an announcement in the electronic public procurement system Prozorro.
As KyivVlada found out after further analysis of procurement documents, the expected cost is 2,30 million hryvnias without VAT, or 2,76 million hryvnias with VAT. The procurement will be financed from the local budget through several programs, including education and emergency response and recovery.
Two generators are to meet the AKSA APD35A CI model or an equivalent. Their rated output is at least 25,6 kW, standby 28 kW. The fuel tank must hold 60 liters, and diesel consumption at full load should not exceed 8 L/hour.
Another generator of type AKSA APD110A CI or similar will have a rated output from 80 kW and standby from 88 kW. The tank capacity should be at least 155 liters. Maximum fuel consumption at full load is 23 L/hour.
The fourth installation is a mobile AKSA APD70BD generator or equivalent on a two-axle trailer. Its rated power should be at least 50,4 kW, standby 56 kW. The fuel tank capacity is from 180 liters, consumption up to 15 L/hour. The trailer must have a load capacity of no less than 1,6 tons, torsion suspension, brakes, and the documents for registration with the Ministry of Internal Affairs Service.
All generators must be three-phase at 400 V and equipped with weatherproof noise-reducing housings. Also provided are engine preheating, batteries, automatic charging, control panel, and automatic transfer switches. The installations are designed for currents of 63, 160 and 125 amperes respectively.
The equipment must be new and ready to operate. Warranty is at least two years or 2 thousand service hours. The price should include delivery, unloading, setup, commissioning, and staff training. The supplier must also provide a service center in Kyiv or within a radius of 100 kilometers from the customer.
The generators must be delivered by 15 December 2026 of the year. The supplier has not yet been determined. Proposals are accepted until 4 October.
For news on Kyiv and Kyiv region purchases last week, watch the KV video.