In downtown Kyiv, in Pechersk, they plan to modernize the street lighting — old mercury and sodium lamps will be replaced with energy-saving fixtures. Work will be carried out in the neighborhood bounded by four streets, with financing of 46,9 million hryvnias (including VAT) provided from the city’s special budget fund.
As reported to KV from the tender documentation, which the editorial office additionally analyzed, the municipal enterprise Kyivmisksvitlo plans to carry out major repairs of the outdoor lighting networks in the Pechersk district of the capital. The work will cover the neighborhood bounded by Lesia Ukrainka Boulevard, Knyaziv Ostrozkykh Street, General Almazov Street, Mechnikov Street, and Klovskyi Descent. Outdated mercury and sodium fixtures will be replaced with LED fixtures. The expected cost of the work is 38 million 409 thousand 271 hryvnias excluding VAT, or 46 million 91 thousand 125 hryvnias including tax. Financing is provided from Kyiv’s special budget fund. The announcement of the open tender was published on 30 October, and the auction is to take place on 17 November.
According to KV, the major repairs will concern outdoor lighting networks connected to feed points PV-1022, PV-1093, PV-1471 and PV-1385. The project foresees replacing the existing fixtures with energy-efficient LED fixtures. The tender documentation states that the works are being carried out for the purpose of energy saving. The contractor must perform construction and installation works in accordance with the project documentation and established technical requirements.
As Kyiv Vlada found, the customer set specific requirements for the lighting equipment. Participants must provide the technical specifications of the proposed fixtures and manufacturers’ documents confirming their compliance. Lighting calculations for the designated sections must also be carried out. The calculations should take into account the mounting height of the fixtures, the location of poles, the length of brackets, and tilt angles. In particular, for one of the sections the mounting height is set at 4,2 meters and the tilt angle at 15 degrees.
KV’s analysis shows that the contractor must ensure that the work is performed in compliance with building codes, electrical installation operation rules, and safety requirements. The procurement is conducted as a single lot. Participants must confirm the availability of the necessary resources and the ability to perform the work without advance payment. The customer set a bid security in the amount of 192 thousand hryvnias. In addition, the winner must provide performance security in the amount of 1% of the contract price. These funds will be returned after proper fulfillment of contractual obligations.
Kyiv Vlada’s publication found that the modernization of the outdoor lighting in Pechersk is planned to be completed no later than 20 December 2027 year. Proposals from potential contractors will be accepted until 10:00 16 November 2026 year. The sole evaluation criterion will be the price excluding VAT. Tender proposals must remain valid for 90 days. After selecting the winner, the enterprise plans to sign a contract for the work. The deputy director for construction of the municipal enterprise Kyivmisksvitlo, Andriy Piddubko, is responsible for carrying out the procurement.
See what the Kyiv city and regional authorities and state institutions purchased in October in KV’s video:
Document: PDF proof of the original version of the news item "Печерськ за 46,9 млн гривень отримає нові лампи на ліхтарях". It records the publication content at the moment of the first scan, the preservation date and the source: KyivVlada.