The Kyiv Regional Administration under the leadership of Mykola Kalashnyk concluded contracts to build protective structures for transformers totaling 1,84 billion UAH without holding tenders. Member of Parliament Yaroslav Zheleznyak reported possible violations in the distribution of subcontracts, the preparation of estimates, and the use of budget funds.
The information was also shared by volunteer Serhiy Sternenko on his Facebook page.
According to published data, contractor organizations have already received 824 million UAH in advance payments. At the same time, work has been documented as completed for approximately 23 million UAH. That represents only 2,8% of the total amount of advances transferred.
A significant portion of the orders was concentrated with two companies — “Consulting-Bud” and “U.B.C.” They accounted for more than 80% of the value of the signed contracts, or about 1,57 billion UAH.
According to Zheleznyak, the owners of these companies, Liubomyra Kozhushko and Ihor Nesteruk, live in the same household.
Kozhushko previously received two suspicions from the police and the NABU in other cases concerning alleged corruption offenses. She was also held in custody. Despite this, the MP alleges that the companies continued to receive new orders and were paid advance payments.
Questions were also raised about construction costs. According to the MP, the estimates for different sites contained nearly identical amounts, and some calculations matched down to the fifth decimal place.
In addition, one contract specified such an amount of reinforcement that, in Zheleznyak’s assessment, physically could not fit into the given volume of concrete.
Sternenko’s post also mentions the use of intermediary companies in the supply chains for materials. He claims that markups on certain goods could have ranged from 15% to 2000%.
Against the backdrop of the situation around the protection of energy infrastructure, former Deputy Minister for Restoration Ruslan Oliinyk reported that he submitted a resignation letter.
The former official accused Mykola Kalashnyk of manipulations and attempts to place responsibility on him for problems in implementing projects to protect energy facilities in the Kyiv region.
The allegations cited are claims by participants in a public conflict, not facts established by a court.
Earlier, StopCor reported that the editorial office sent an information request to Minister Mykola Kalashnyk regarding the circumstances of the contracts concluded for protecting Kyiv region energy facilities. Journalists also asked for an explanation about Ruslan Oliinyk’s dismissal and statements by entrepreneur Vladyslav Sokolov. Kalashnyk previously called the publications around this story a discrediting campaign.
Document: PDF proof of the original version of the news item "Захист енергооб’єктів Київщини за 1,84 млрд грн: Железняк заявив про можливі порушення в контрактах". It records the publication content at the moment of the first scan, the preservation date and the source: NARDEP 24.